Exploring the impact of risks on road construction quality: an AHP model study

  • Affiliations:

    Hanoi University of Mining and Geology, Hanoi, Vietnam

  • *Corresponding:
    This email address is being protected from spambots. You need JavaScript enabled to view it.
  • Received: 2nd-Jan-2023
  • Revised: 15th-May-2023
  • Accepted: 9th-June-2023
  • Online: 30th-June-2023
Pages: 70 - 78
Views: 858
Downloads: 6
Rating: 5.0, Total rating: 1
Yours rating

Abstract:

The construction industry plays a role in the development of countries. The progress of this industry mainly depends on the quality of construction works, which is closely related to the longevity of the work. A risk assessment of construction quality is a comprehensive assessment of the level of risks and the construction contractor faces during the construction process. Risk factors affect the quality of work in the aspect of labor, equipment and machinery, material, constructional technology, environment, etc. Based on these factors, the authors build an index system to evaluate the quality of works according to experts. Quality is one of the factors to evaluate the success of construction projects. The level of success of the construction industry depends on many quality performances. The method used in this article is the analytical hierarchical method (AHP) for quantitative analysis, which has the function of comparing and selecting alternatives without requiring big data, etc. This method will also be chosen to satisfy the set of criteria. Based on the principle of comparing pairs of criteria, the AHP method analyzes, evaluates, synthesizes, and answers the question "Which criterion affects the quality of the work during the construction process?". This study is conducted to scrutinize the factors that harm construction projects. The results of the study evaluating over 15 criteria show that the influencing factor due to equipment and machinery assessed has the greatest influence on the quality of the work.

How to Cite
Dang, T.Trung, Nguyen, P.Duyen and Tran, M.Tuan 2023. Exploring the impact of risks on road construction quality: an AHP model study. Journal of Mining and Earth Sciences. 64, 3 (Jun, 2023), 70-78. DOI:https://doi.org/10.46326/JMES.2023.64(3).08.
References

Abd El-Razek, M. E., Bassioni, H. A., and Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of construction engineering and management, 134(11), 831-841.

Cao, Y. (2010). Quality Control of Construction Projects.” Degree Programme in Industrial Management (Doctoral dissertation, Thesis, Savonia University of Applied Sciences, Business and Engineering, Varkaus). Savonia University of Applied Sciences, Business and Engineering, Varkaus. 53 pages.

Choudhry, R. M., Aslam, M. A., Hinze, J. W., and Arain, F. M. (2014). Cost and schedule risk analysis of bridge construction in Pakistan: Establishing risk guidelines. Journal of Construction Engineering and Management, 140(7), 04014020.

Gonzalez, P., González, V., Molenaar, K., and Orozco, F. (2013). Analysis of causes of delay and time performance in construction projects. Journal of construction engineering and management, 140(1), 04013027.

Gündüz, M., Nielsen, Y., and Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of management in engineering, 29(2), 133-139.

Larsen, J. K., Shen, G. Q., Lindhard, S. M., and Brunoe, T. D. (2016). Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of management in engineering, 32(1), 04015032.

Mahamid, I., Bruland, A., and Dmaidi, N. (2012). Causes of delay in road construction projects. Journal of management in engineering, 28(3), 300-310.

Project Management Board of Nam Cao University Urban Area (2020), Explanation of construction drawings of Nam Cao University Urban Area, Ha Nam (Vietnamese version).

Saaty, T. L. (2008). Decision making with the analytic hierarchy process. International journal of services sciences, 1(1), 83-98.

Saaty, T. L. (1980).The Analytic Hierarchy Process Mcgraw Hill, New York. Agricultural Economics Review, 70. 285-308.

Szymański, P. (2017). Risk management in construction projects. Procedia engineering, 208, 174-182.

Tafazzoli, M. (2017). Dynamic risk analysis of construction delays using fuzzy-failure mode effects analysis (Doctoral dissertation, University of Nevada, Las Vegas).

Zou, P. X., Zhang, G., and Wang, J. (2007). Understanding the key risks in construction projects in China. International journal of project management, 25(6), 601-614.

Xu, X., Wang, J., Li, C. Z., Huang, W., and Xia, N. (2018). Schedule risk analysis of infrastructure projects: A hybrid dynamic approach. Automation in Construction, 95, 20-34.